On a cloudy but warm Saturday morning, 20 hikers gathered at the boat launch area at Duchman lake. Megan Henderson was our leader for the day. I think we had 1-2 new hikers with us. We proceeded back up the lane, and into the woods, following a new trail that is a re-route. We covered about 4 miles, and did see a few drops of water dribbling at a water fall. We ate lunch at the big shelter bluff/cave, where we also took the group picture. We headed back..’up top” of some of the areas we had been during the morning. Megan decided to get out to the road, and walk back in, to avoid any chances of us getting wet. We did pick up trash along the roadway, coming back to the vehicles. 

Saturday, November 1, 2025 Hike Announcement

The River to River Trail Society announces its 4th public hike of the 2025 Fall hiking season on Nov. 1st.  Hiking: Dutchman Lake (Johnson County). This hike is free and open to the public. This will be a moderately difficult loop hike approximately 5 miles in length approximately 4 hours hiking time. The leader of this hike can be reached at 618-967-0019 for more information. Hikers should meet at 10:00 am at Dutchman Lake. This hike is intended for people in very good health who have done some hiking. Hiking sticks and boots or sturdy shoes are recommended. Hikers should bring their own water and snacks. No dogs please. There are stream crossings which will require hikers to walk rocks in order to cross streams and the rocks may be slippery if the rocks are wet. Some steep grades are on this hike. Some slick rock on this hike which may be slippery if it has rained. This hike may be tracked using the Avenza App. map R2R 16 or SNF Vienna Quad. map. For a map to the meeting location at Dutchman Lake click this blue link Dutchman Lake and a map will open up, and then click the Directions button and a driving map will be created which will allow you to plan your driving directions to the meeting area. Prior to participating in any hikes, the River to River Trail Society requests that all hikers read the 2023 Trail Society Waiver which can be found on the River to River website at the following link River to River Trail Society Information and then sign off on this waiver prior to the beginning of the hike. A copy of the waiver will be at the Dutchman Lake meeting area for your signature.

Dutchman Lake R2R Trail Reroute Update

As a final update to the subject reroute, the entire new trail is now completed and blazed. The trail maps 15 & 16 in Avenza have been updated and now are available for downloading to your device. There is still some minor trail work to be done on the west side of the Dutchman Lake Dam, but it should not affect any trail users. However, if you do encounter the Forest Service employees working on the trail with their small dozer and excavator, please exercise caution when walking around the crew. As a reminder, the trail changes are shown in the following image.

Dutchman Lake Reroute Construction Starts

On October 29, 2024, the Forest Service trail crew started construction of the River to River (R2R) Trail reroute in the Dutchman Lake area. This reroute is a continuation of the reroute that was started in February 2023 when a 1/2 mile section of the trail west of the lake was rerouted around the pine forest section. The Trail Society and Forest Service have been working on this reroute for several years now. The following image is a map of the area showing the work plan.

Work started at Dutchman Lake Road heading west. The future trail will cross Fishing Hole Lane and meander it way around the bluffs and waterfalls to slowly descend down the hill toward the dam. Most of the route follows many of the existing user made trails the area. This reroute will affect existing maps 15 & 16 in the R2R Trail bundle if your are using Avenza and chapter 10 of the Trail Guide. When complete, the reroute will add about 1.2 miles to the length of the R2R trail through the area.

The concerns that prompted this complete reroute include the following:

  • For the first 1/2 mile east of Twinz Lane on the west side of the area was reroute the pine forest because the pines started falling because they were getting too old. The problem started back in 2018/2019 when upwards of 70+ trees fell requiring a significant work days in November 2019 to clear the trail. More trees continued to fall in the following years and due to the lack of a tree canopy the trail became impassable due to overgrown weeds. In late 2022 the Forest Service agreed a reroute was necessary and that work was completed on a Society work day in February 2023. See black oval in map above.
  • For the first 3/4 mile east of fishing hole lane, the existing trail traveled through a 100′ wide clearing between pine forests on each side. In this clearing area the trail would get extremely overgrown with weeds in the summer and early fall to the point that the trail could not be followed. Also, in recent years there have been several pines that have started falling over that section of trail requiring numerous work days to clear them. See the red oval in the map above.
  • The last to problem areas are where the trail is too steep to meet FS standards. These steep sections of trail are subject to constant erosion problems which has been occurring for years. One of these areas is shown in the brown oval in the above map. The second area is where the trail goes back uphill after crossing the dam.

Trail maps 15 & 16 will be officially reissued once construction is complete and the blue “i” trail assurance markers are installed along the new route and markers removed from the existing route. Similarly, an update to the Trail Guide will be issued to include this reroute and the Cedar Lake Reroute completed during the summer of 2024.

Trail work started with the dozer working along the trail to clear the route and install drainages.

Following behind the dozer is a mini excavator that fine tunes the trail and drainages.